I'd guess most plumbers set their rate by looking at what other plumbers charge. That tells you what the market will pay. It doesn't tell you whether you'll make any money at that price.
So work it out in this order: what you need, then what the market pays, then how you'll charge.
The short version
- Your charge-out rate comes from your costs and your billable hours, not from your wage.
- Published UK guides put plumbers at roughly £40 to £70 an hour. Treat those as guides, not facts.
- The number that moves your rate most is the share of your week you can actually charge for.
- Use a fixed quote for jobs you can see, and an estimate for jobs you can't.
- A job agreed in a customer's home can carry a 14-day right to cancel. Urgent repairs are different.
What UK plumbers charge
Here's what the published guides say. I've kept them side by side, because they don't agree.
| Measure | Checkatrade | WaterSafe | MyJobQuote |
|---|---|---|---|
| Hourly rate | £40 to £60 | £40 to £70 | About £60 (emergency guide) |
| Day rate | £325 to £375 | £250 to £400 | About £380 (emergency guide) |
| Emergency call-out | £100 to £120 | £60 to £120 | Around £75 |
Two warnings. Checkatrade and MyJobQuote both sell leads to tradespeople, and none of these guides shows its method or sample. Checkatrade also gives different day rates in different guides. Use these numbers to sense-check your price. Don't use them to set it.
Location matters too. MyJobQuote's city table puts London at £75 to £95 an hour, against £55 to £70 in Leeds, Birmingham and Liverpool. It sits on an emergency plumbing page, so it may run high.
Work out your real hourly rate
You need three numbers: what you want to earn, what the business costs to run, and how many hours you can bill.
Worked example: a sole trader in Leeds (made-up figures)
Harris Plumbing is an example business. Swap in your own numbers.
| Line | A year |
|---|---|
| What the owner wants to pay themselves | £40,000 |
| Van, fuel and insurance | £6,500 |
| Public liability and tools insurance | £700 |
| Tools and replacing them | £1,500 |
| Phone, software and website | £1,800 |
| Accountant | £900 |
| Marketing | £2,400 |
| Training and registrations | £1,200 |
| Workwear, parking and sundries | £1,000 |
| Subtotal | £56,000 |
| 10% profit, so the business has a buffer | £5,600 |
| Total to recover | £61,600 |
Hours: 46 working weeks at 40 hours is 1,840 hours. If 60% of that can be charged, that's 1,104 billable hours.
£61,600 divided by 1,104 is about £56 an hour, before VAT and before materials.
That sits inside the published range, which is a good sign. It also shows why a plumber on £45 an hour can be busy and still short of money. At £45 an hour, those same 1,104 hours bring in £49,680. That's £11,920 less than the example needs.
Billable hours do most of the work
Most of the week isn't billable. Driving, buying parts, pricing, chasing and invoicing all take time, and nobody pays you for them directly. The 60% above is my working assumption, not a published figure. Track two normal weeks and use your own.
| Share of hours you can bill | Billable hours a year | Rate needed |
|---|---|---|
| 50% | 920 | £67 |
| 60% | 1,104 | £56 |
| 70% | 1,288 | £48 |
Moving from 50% to 70% takes £19 an hour off the rate you need. That's why admin isn't a side issue. Every hour you stop spending on calls and chasing either becomes a billable hour or an hour back with your family.
Choose how you'll charge
| Method | Best for | Watch out for |
|---|---|---|
| Hourly rate | Fault-finding, where you can't see the problem yet | Customers feel the clock. Agree a minimum charge and say what it covers. |
| Day rate | Larger jobs and work for other trades | Agree start and finish times, and who pays for lost time. |
| Fixed price | Jobs you've done many times | You carry the risk if the job grows, so write down what's included. |
| Call-out plus labour | Emergencies and out-of-hours work | Say the full charge before you travel. |
For regular jobs, I'd move towards a fixed price list. Customers like knowing the number. It also rewards you for being quick, where hourly pay punishes it.
Here's a tap, using the example rate. Allow 1.5 hours on site: £84 at £56 an hour. Add a £60 tap with a 20% mark-up: £72. That's £156 before VAT. Checkatrade's tap guide shows £140 to £260 for most tap replacements, but it also gives £140 as labour only, and its dates conflict, so check it against your own area.
Quote or estimate?
These words mean different things to a customer, so use the right one.
- A quote is a fixed price. Citizens Advice tells customers to ask for one.
- An estimate is a rough guess. If the final bill is much higher, the customer can dispute it, and the price should be reasonable.
- If no price was agreed, the law says the customer pays a reasonable price, and no more.
Citizens Advice says a contractor can't charge more than a quote unless the customer asks for extra work, agrees to pay for extra work they were told about, or the contractor made a genuine calculation mistake. That's from Citizens Advice's Scotland page. We couldn't open the England version, so check it if you're in England or Wales. So put in writing what's included, what isn't, and how you'll handle surprises.
Hidden pipework is the classic one. A simple line works: "If we find further faults behind the wall, we'll stop, show you and agree the price before we carry on."
The 14-day rule that catches plumbers out
If you agree a job in a customer's home, that's usually an off-premises contract under the Consumer Contracts Regulations 2013. If they accept later by phone, email or text, different rules may apply, so don't assume you're in the clear. Ask your trade association.
What this means in practice
- The customer normally has 14 days to cancel. On a service, that runs from the day you agree the job. If the job includes goods, such as a new boiler, the period may run differently, so check with your trade association.
- You must give them the cancellation information on paper, or another durable form if they agree.
- If you don't, the cancellation period can run for up to 12 months longer, and failing to give the information is a criminal offence.
- Don't start inside the 14 days unless they expressly ask you to, on paper or in another durable form.
- If they ask you to start and later cancel, they pay a proportionate amount for the work done. If you skipped the paperwork, they may pay nothing.
There are two exceptions that matter to plumbers. There's no right to cancel where the customer specifically asked you to visit for urgent repairs or maintenance, though anything extra you sell on that visit isn't covered by the exception. And off-premises contracts of £42 or less fall outside these rules.
Your quote template should include the cancellation notice and a line the customer signs if they want you to start straight away. A burst pipe isn't the problem here. A £3,000 boiler swap agreed at the kitchen table is. If a customer cancels on day 10 and you never gave them the notice, you could be out of pocket.
This is general information, not legal advice. Your trade association may have a compliant form.
Don't forget VAT
You must register for VAT if your taxable turnover passes £90,000 in any 12 months, or you expect it to in the next 30 days. Once you're registered, domestic customers usually pay 20% on top, or you absorb it. Some work can be taxed differently, so ask your accountant.
At the example rate, £56 becomes £67.20 with VAT. If you're close to the threshold, price for it before you cross it. Putting prices up the month you register is a hard conversation. Get your accountant to run the numbers first.
Raise your prices without losing the good customers
- Put your rates up once a year, on a set date.
- Tell your regular customers first, in a short and plain message.
- Drop the jobs you hate pricing for, or price them so you're happy either way.
- Follow up every quote. A quote nobody chases is often lost on silence, not on price.
Our text templates for plumbers include a quote follow-up you can copy.
Questions plumbers ask
What's a fair hourly rate for a plumber in the UK?
Published guides sit around £40 to £70 an hour, with London higher. Your fair rate is the one that covers your costs at your real billable hours. For the example above, that's about £56 before VAT.
Should I charge for quotes?
Most customers expect a free quote on larger work. A fair middle ground is to give a free ballpark from photos, and charge for a fault-finding visit, taking that fee off the job if they go ahead. That's my view, not a rule.
How much should I mark up materials?
There's no set figure. Pick a mark-up that covers the time you spend buying, collecting and returning parts, plus the risk of warranty returns. Then use it every time.
Can I change a quote after I've started?
Only in limited cases. Citizens Advice says the customer must have asked for the extra work, agreed to pay for it after being told, or there must have been a genuine calculation mistake. Agree any change in writing before you do the work. A text will do as a record.
Sources
- Checkatrade, plumber cost guide (June 2026, sells leads to trades)
- Checkatrade, tap installation cost (dates conflict on the page)
- WaterSafe, how much does a plumber cost?
- MyJobQuote, emergency plumbing costs (7 October 2026, sells leads to trades)
- Citizens Advice, before you get work done on your home (Scotland page)
- Citizens Advice, problems with home improvements
- Consumer Rights Act 2015, section 51
- Consumer Contracts Regulations 2013
- Regulation 28, urgent repairs
- Business Companion, off-premises sales
- GOV.UK, register for VAT
Prices and rules change. Check the source before you rely on a figure. This is general information, not legal, tax or financial advice.