Published guides put an electrician at roughly £40 to £70 an hour outside London. Use that as a sense check and nothing more. It won't tell you if you're making money at that price, and neither will the van down the road.
Start from what you need, compare it with the market, then decide how each type of work gets charged. A fault, a consumer unit and an EICR carry very different risks, so one rate for all three is a mistake.
The short version
- Your rate comes from costs and billable hours, not from a wage.
- The guides disagree, and one survey average was just £38 an hour.
- Fix the price on work you can see. Charge time on fault-finding.
- A cheap one-off EICR can lose money. Batched EICRs often don't.
- A board sold at the kitchen table can carry a 14-day right to cancel, even if they first rang about an urgent fault.
What the published guides say
They don't agree, so here they are side by side.
| Measure | Fantastic Services | Whito | Best Builders | Logic4training survey |
|---|---|---|---|---|
| Hourly rate | £40 to £60 | £40 to £60 | £45 to £70 | £38 average |
| Day rate | £220 to £400 | £300 to £360 | Not used | £312 average |
| Call-out | £60 to £120 | £80 to £100 | Not used | Not used |
| Consumer unit | £450 to £750 | £350 to £750 | £550 to £1,100 | £890 average |
| EICR | £120 to £350 | £150 to £300 | Not used | From around £250 |
Read them with care. Fantastic Services sells electrical work and Whito runs a directory. Best Builders gives no date or method. Logic4training is a training firm surveying people it trained, and its hourly average dropped from £44 in 2025. These are outside-London figures where a guide splits them: Fantastic Services puts London at £55 to £75 an hour, and Best Builders says £65 to £100 for London and the South East. Checkatrade's hourly page still refers to 2021, so I've ignored it.
Build your rate from the van up
The sum takes three inputs: the pay you want, the cost of running the business, and the hours a customer will actually pay for.
Worked example: a Norwich sole trader (made-up figures)
Wethercote Electrical doesn't exist. Put your own numbers in its place.
| Line | A year |
|---|---|
| What the owner wants to pay themselves | £42,000 |
| Van and fuel | £7,200 |
| Public liability, indemnity and tools insurance | £900 |
| Test kit, calibration and tools | £1,400 |
| Scheme fees, certificates and training | £1,300 |
| Phone, software and website | £1,700 |
| Accountant | £900 |
| Marketing | £2,000 |
| Workwear, parking and sundries | £800 |
| Subtotal | £58,200 |
| 10% profit, so the business has a buffer | £5,820 |
| Total to recover | £64,020 |
45 weeks at 40 hours gives 1,800 hours. If 60% of those can be charged, that's 1,080.
£64,020 ÷ 1,080 = about £59 an hour, before VAT and materials.
That's inside the published range, and it shows how someone on £48 an hour can be flat out and still short. Those 1,080 hours at £48 bring in £51,840, which is £12,180 under what this example needs.
The £42,000 sits close to the £39,039 median that Logic4training quotes from ONS figures. An employee on that money doesn't buy a van, a tester or insurance, though.
The hours you never bill
That 60% is my working assumption, not a published figure. Test results, tenants who won't answer, wholesaler runs and certificates all eat the week without appearing on an invoice. Track two normal weeks and use what you find.
| Share of hours you can bill | Billable hours a year | Rate needed |
|---|---|---|
| 50% | 900 | £71 |
| 60% | 1,080 | £59 |
| 70% | 1,260 | £51 |
A swing from 50% to 70% takes £20 off the rate. Finishing certificates on site, not at home at night, is a pricing decision.
One charging method won't fit every job
| Work | How I'd charge | Watch for |
|---|---|---|
| Fault-finding | Call-out plus time, with a stated first-hour charge | You can't see the cause, so name the charge before you set off. |
| Small works | Fixed price with a minimum | One vendor guide suggests about two hours or £120. |
| Consumer units | Fixed price | Say what happens if testing finds faults on existing circuits. |
| Rewires | Fixed price by room, exclusions in writing | Making good. Be clear who does it and who pays. |
| EICRs | Fixed by property size, remedials quoted apart | Unknown circuit counts and poor access. |
| Work for builders | Day rate or per plot | CIS deductions and retentions. |
A consumer unit, costed
Worked example (made-up figures)
6.5 hours for the change, testing and paperwork: 6.5 × £59 = £383.50.
A board and devices costing you £220, marked up by 20%: £264.
Total £647.50 before VAT, or £777 with it.
That lands inside the Fantastic Services and Best Builders ranges. It also shows why an hourly figure misleads. The customer hears "£59 an hour", when you're selling a tested board, a certificate and a notification.
Trade2Base, a vendor, calls mark-ups of 20% to 35% typical on standard items. I've no independent figure, so treat it as a starting point. Count scheme costs too: NICEIC lists online certificates at £1.60 plus VAT per installation.
One line saves a lot of arguments: "If testing shows faults on existing circuits, I'll stop, show you and agree the price before carrying on." A new board can expose old faults that never tripped anything.
Why a £220 EICR can lose money
My clearest opinion in this guide: a cheap one-off EICR is often a loss, and pricing it low to fish for remedial work is a bad habit.
Worked example (made-up figures)
A house at £220 takes 3.5 hours on site and an hour to write up. 4.5 hours works out at about £49 an hour, roughly £10 below the £59 rate.
Three flats for one agent on one day, at £180 each, take 2.5 hours apiece including the report. £540 for 7.5 hours is £72 an hour.
The cheaper job pays better because the driving's gone. Batch by postcode, and price by bedrooms or circuits.
Keep the report honest, too. If it calls for remedial work, a private landlord in England has 28 days or less, so your coding costs them real money. The code must come from the installation, never from what you'd like to sell. Quote remedials separately and let the landlord choose who does them. I'd expect that to win you more agency work than sharp pricing ever will.
Fixed price, or time charge?
Customers hear these words differently, so choose on purpose.
- A quote is a fixed price.
- An estimate is a best guess, and a final bill far above it can be disputed.
- With no agreed price, the Consumer Rights Act 2015 says a consumer pays a reasonable one.
A time charge or estimate is the honest way to sell fault-finding. For a board swap, I'd fix the price and use the line above about existing circuits.
The kitchen table trap
A job you agree in a customer's home is usually an off-premises contract under the Consumer Contracts Regulations 2013.
In practice
- They normally get 14 days to cancel.
- The cancellation information must reach them on paper, or another durable form if they agree, before they're bound.
- Skip it and the period can run up to 12 months longer. Failing to give it is also a criminal offence.
- Wait out the 14 days unless they expressly ask you to start, on paper or in another durable form.
- If they ask you to start and later cancel, they pay a fair share for what's done. If you started without that request, or without giving the information, they pay nothing.
Urgent repairs are the big exception for this trade. There's no right to cancel where the customer specifically asked you out for urgent repairs or maintenance, but regulation 28 doesn't stretch to extra services, or goods beyond the necessary parts.
So picture a tripping RCD callout, which counts as urgent, where you find an old fuse board and price a new consumer unit at the table. The callout falls under the exception. The board probably doesn't, so hand over the notice. Contracts of £42 or less sit outside these rules.
Landlords are murkier. A company buying an EICR isn't a consumer. An individual with one flat may or may not be, so I'd give the notice anyway. Ask your scheme or trade body if it has a form. This is general information, not legal advice.
VAT on electrical work
Registration is compulsory once taxable turnover goes over £90,000 in any 12 months, or you expect that in the next 30 days. At the example rate, £59 becomes £70.80.
Three points are particular to this trade:
- HMRC's Notice 708/6 gives solar panels and batteries in homes a zero rate to 31 March 2027, then 5% from 1 April 2027. It doesn't mention EV chargers, so don't assume they qualify.
- The domestic reverse charge can apply when you and your customer are both VAT-registered and the work is reported under CIS.
- CIS deductions on work for builders hit your cash flow, so allow for them.
Ask your accountant which treatment fits each job.
Putting your rates up
- Pick one date a year.
- Tell regular customers and agents first, in a short message.
- Set a minimum charge, and stop losing money on one-socket visits.
- Chase quotes. My guess is that silence loses more of them than price does.
The text templates include a quote follow-up you can copy.
Questions electricians ask
What hourly rate should an electrician charge?
Whatever covers your costs at your real billable hours. Guides cluster around £40 to £70 outside London and higher inside it. The example above needs about £59 before VAT.
Should I charge for quotes?
Most people expect planned work to be quoted free. I'd give a free ballpark from photos and charge for fault-finding. That's my view, not a rule.
What's a normal price for an EICR?
Guides run from about £120 to £350 for a home, more in London. Price by size and circuits, then check what it pays per hour once the report's written.
Should remedial work be in the EICR price?
No. Keep it apart, so the landlord sees what the report found and stays free to use someone else.
What if the job changes once I've started?
Agree the change in writing before doing the extra work. A text is enough of a record.
Sources
- Fantastic Services, electrician cost guide (24 September 2026, sells electrical work)
- Whito, how much do electricians charge? (undated, directory)
- Best Builders, how much do electricians charge? (undated)
- Logic4training, electrician day rates (15 June 2026, training provider)
- Checkatrade, electrician hourly rate (undated, title refers to 2021, not used for rates)
- Trade2Base, electrician pricing guide (26 May 2026, vendor)
- NICEIC, Domestic Installer scheme
- Electrical Safety Standards Regulations 2020, regulation 3
- Consumer Rights Act 2015, section 51
- Regulation 28, urgent repairs
- Business Companion, off-premises sales (February 2025)
- GOV.UK, register for VAT
- HMRC, VAT Notice 708/6 (31 January 2024)
- HMRC, VAT domestic reverse charge
Prices and rules change. Check the source before you rely on a figure. This is general information, not legal, tax or financial advice.